ARTICLE · 18 APRIL 2020

COVID-19 Update: Suspension Of Limitation And Procedural Periods In Ontario And The Construction Act

With recent changes implemented in response to the COVID-19 pandemic, construction liens in Ontario no longer expire in the ordinary course.

CanadaReal Estate and Construction

With recent changes implemented in response to the COVID-19 pandemic, construction liens in Ontario no longer expire in the ordinary course. This will have significant implications for owners of a property on which a construction project is taking place, financial institutions and mortgagees financing construction projects, general contractors and subcontractors.

On March 20, 2020, the Lieutenant Governor in Council made an order under s. 7.1 of the Emergency Management and Civil Protection Act  (the “EMCPA”) suspending limitation periods and procedural time periods in Ontario (the “Suspension Order”). The suspension is retroactive to March 16, 2020 and will last “for the duration of the emergency”. Section 7.1(4) of the EMCPA provides that the maximum suspension period is 90 days. However, the suspension can be further renewed in certain circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from