Alberta Prompt Payment And Construction Lien Act—Court Confirms 180 Day Deadline To Commence An Action

Bennett Jones LLP
Bennett Jones LLP
Contributor
Bennett Jones LLP

Bennett Jones LLP

Bennett Jones is one of Canada’s premier business law firms. With deep experience in complex...

View firm profile
Explore more from Bennett Jones LLP

Benjamin Franklin once said, "lost time is never found again".

CanadaReal Estate and Construction

Benjamin Franklin once said, "lost time is never found again". A recent case from the Alberta Court of King's Bench confirms the truth of this statement for any lienholder seeking to initiate a Statement of Claim past their agreed upon deadline to do so.

Facts

In Lesenko v Wild Rose Ready Mix Ltd, 2023 ABKB 148, the Lesenkos' hired a contractor who subcontracted with Wild Rose to supply concrete. Wild Rose filed two builder's liens in October 2019 for non-payment reasons. A month later, the parties entered into a consent order (the Order) under section 48 of what is now the Prompt Payment and Construction Lien Act (the PPCLA). An order under section 48 allows the court to order the registration of a lien be removed from title where the property owner pays security into court.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from