ARTICLE · 05 JUNE 2024

Throwing Good After Bad Can Be Okay: BC Court Of Appeal Determines Owner's Payment Did Not Have Retroactive Effect On Builders Lien Liability

This bulletin covers a recent decision from the BC Court of Appeal in Pinnacle Living (Capstan Village) Lands Inc. v. Fairway Recycle Group Inc., 2024 BCCA 172.

CanadaLitigation, Mediation & Arbitration

This bulletin covers a recent decision from the BC Court of Appeal in Pinnacle Living (Capstan Village) Lands Inc. v. Fairway Recycle Group Inc., 2024 BCCA 172. The decision determined that an owner entering into an agreement with a subcontractor to pay outstanding amounts owed by another subcontractor did not alter the owner's ability to discharge the subcontractor's lien claim under section 23 of the Builders Lien Act.

Background

The owner of a mixed-use project engaged a head contractor for a project. The contractor engaged an excavation subcontractor for the project, who in turn engaged another subcontractor to perform disposal work for the project.

The disposal subcontractor performed the work on the project, but the excavation subcontractor failed to pay the invoices issued by the disposal subcontractor.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from