On November 10, 2022, the Supreme Court of Canada (SCC) issued
its much-anticipated decision in Peace River Hydro
Partners v Petrowest Corp, 2022 SCC 41, addressing a key intersection of
insolvency and arbitration law—whether and in what
circumstances a contractual agreement to arbitrate should give way
to the public interest in the orderly and efficient resolution of a
court-ordered receivership. The nine-member SCC panel unanimously
determined (with concurring reasons) that, in this case, it must,
and dismissed the appeal with costs to the Receiver.
The decision clarifies the law on when mandatory arbitration
clauses will be enforced in the context of insolvency proceedings,
and is important for parties to commercial contracts, insolvency
practitioners and the arbitration practice generally. As noted by
the SCC, it is "not unusual now for a commercial party to find
itself in a dispute governed by an arbitration agreement with an
insolvent or bankrupt counterparty."