ARTICLE · 14 MAY 2019

The Superior Court Confirms The Criteria Related To The Termination For Cause Of A Subcontracting Agreement And Resulting Damages

In July 2005, Litostroj executed two identical subcontracting contracts with Ideal for the design, production, installation, and activation of the generators.

CanadaLitigation, Mediation & Arbitration

Upon examining if there were sufficient grounds to terminate the subcontracting agreement between Litostroj Hydro Inc. ("Litostroj") and Ideal Electric Company ("Ideal") for the production of generators in the context of Hydro-Québec's project to build two hydroelectric plants, the Superior Court (the "Court"), presided by Honorable Chantal Tremblay, SCJ, dismissed Ideal's claim in its entirety in the case I.E. Liquidation Inc. v. Litostroj Hydro Inc. In addition, the Court confirmed that the governing principles in the matters of: termination for cause, abuse of right in the execution and termination of contracts, the evaluation of the value of work in such a context, and lawful notification.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.