Court Of Appeal Reminds Industry: Change Orders May Be Approved By Conduct Or Acquiescence

MLT Aikins LLP
MLT Aikins LLP
Contributor
MLT Aikins LLP

MLT Aikins LLP

FIRM OVERVIEW MLT Aikins is a full-service business law firm of more than 375 lawyers with a deep...

View firm profile
Explore more from MLT Aikins LLP

The Manitoba Court of Appeal has issued an important reminder for the construction industry.

CanadaLitigation, Mediation & Arbitration

This article first appeared in Build Manitoba, a publication of the Winnipeg Construction Association.

The Manitoba Court of Appeal has issued an important reminder for the construction industry.

Change orders (extra work or modifications to a contract) may be deemed approved, even where strict contractual procedures for approval are not followed.

For example, although a contract may explicitly require formal, signed approval by an owner for all change orders, the owner may still be held responsible for paying despite not personally approving the work. In such circumstances, change orders may be deemed approved if the work was approved or directed by a consultant or contractor who was delegated significant authority, and/or, if the owner remained silent despite awareness that the change order work was proceeding.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from