On February 1, 2021, the Government of Alberta launched Period 5
and Period 6 of the Site Rehabilitation Program (SRP), including
additional information within the updated Site Rehabilitation
Guidelines.
As noted in our earlier
blog post,
following update, and discussions of
Period 2,
Period 3 and
Period 4, the SRP administers funding to eligible oil field
service contractors completing reclamation and abandonment work in
the province.
As of February 12, 2021, Alberta reports that $310.3 million of
the of the $1 billion in federal funding has been approved and is
being allocated to 633 Alberta-based companies.
Update on Period 3 and Period 4
Period 3 (which allocated maximum funding of $139,000 by
licensee) and Period 4 (which provided funding for licensees with
confirmed and proposed Area-Based Closure Plans) both remain open
until March 31, 2021, or until licensee funding has been completely
allocated. For more details, please see our earlier