This case demon­strates how the Court deals with two con­struc­tion con­tracts and decides which one binds the parties.

AustraliaReal Estate and Construction

Introduction

In the recent decision of Stepanoski v Aslan [2018] NSWSC 1160, the New South Wales Court of Appeal had to grapple with whether:

  1.  the parties involved were bound by the first building contract that they signed; or
  2. whether the subsequent contract, which was signed by the parties later and backdated to the date of the earlier contract, replaced the first contract.

The facts

On 14 October 2014, the plaintiffs entered into a cost-plus building contract (Cost-Plus Contract) with the defendant builder in respect of the construction of two residences on land that was owned by the plaintiffs.

In short, a costs-plus contract is a contract where the builder is paid the actual cost of work undertaken plus a percentage over and above those costs on account of margin and preliminaries. These contracts can be used when the total amount payable to the builder cannot be reasonably determined at the time of entering into the contract, or the scope of the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For further information please contact:

Michael Byrnes, Partner
Phone: + 61 2 9233 5544
Email: [email protected]