Stra­ta Plan 92183 v Sam­do­ra Pty Ltd [2026] NSWSC 406 'Substantive Control' Over Works & S37 Of The DB&P Act

A recent NSW court case examines when developers and builders can be held liable under section 37 of the Design & Building Practitioner's Act 2020 for defective building work. The decision clarifies what constitutes 'substantive control' over construction work and establishes the evidentiary threshold required to prove breach of the statutory duty of care.

AustraliaReal Estate and Construction

In this case, the plain­tiff (Stra­ta Plan 92183) brought pro­ceed­ings alleg­ing defec­tive res­i­den­tial build­ing work in rela­tion to 9 town hous­es locat­ed in Manger­ton, NSW.

Rel­e­vant­ly SP92183 claimed that both the builder’s direc­tor (Mr Nas­sif) and the developer’s direc­tor (Mr Chah­wan) had both breached their duty to exer­cise rea­son­able care to avoid eco­nom­ic loss caused by defects as pro­vid­ed for by sec­tion 37 of the Design & Build­ing Prac­ti­tion­er’s Act 2020 (DB&P Act).

Claim against Mr Chah­wan (devel­op­er) for breach of s37 duty of care

SP92183’s claim against Mr Chah­wan was based on the premise that Mr Chah­wan had car­ried out ‘con­struc­tion work’ (as defined by s36 of the DB&P Act), in rela­tion to the repair work, because he had been ‘super­vis­ing, coor­di­nat­ing, project man­ag­ing or oth­er­wise hav­ing sub­stan­tive con­trol over the car­ry­ing out of [build­ing work]’.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For further information please contact:

Michael Byrnes, Partner
Phone: + 61 2 9233 5544
Email: [email protected]

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from