ARTICLE · 24 DECEMBER 2025

One development, two towers and two occupation certificates (one interim and one final): when does the Home Building Act statutory warranty period commence?

Recent case confirms that in interdependent strata developments, statutory warranty periods run from completion of the whole building, not individual stages.

AustraliaReal Estate and Construction

Most proceedings brought by homeowners and owners corporations against builders involve a claim for breach of the statutory warranties contained in section 18 of the Home Building Act 1989 (NSW) (HBA).

The HBA statutory warranties, implied into every contract to do residential building work and which are well known to most, can be found here.

Owners have a statutory time limit for commencing proceedings for a breach of a statutory warranty.

Proceedings seeking to invoke the statutory warranties under the HBA must be commenced 'before the end of the warranty period for the breach'. (HBA, s18E(1)(a))

The 'warranty period' is six years 'for a breach that results in a major defect in the residential building work' and two years in 'any other case'. (HBA, s 18E(1)(b)).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For further information please contact:

Michael Byrnes, Partner
Phone: + 61 2 9233 5544
Email: [email protected]

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from