The Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) is about to undergo some changes. Those changes will apply to construction contracts in New South Wales entered from 21 October 2019.

What are the changes?

Reference dates are gone

There are no more reference dates. The concept of a 'reference date' will be removed from the Act, so that a person a person who has undertaken to carry out construction work, or to supply related goods or services, under a construction contract is generally entitled to a progress payment on a monthly basis.

Subcontractors get paid sooner

A progress payment to be paid to a subcontractor under a construction contract is due and payable no later than 20 (instead of the current 30) business days after the subcontractor makes a payment claim for the payment. There is no change to the requirement for a progress payment to be made by a principal to a head contractor no later than 15 days after the head

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For further information please contact:

Michael Byrnes, Partner
Phone: + 61 2 9233 5544
Email: [email protected]

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from