This powerful mechanism at the heart of the SoP Act has led to many arguments in regards to the time of service of a payment claim.

AustraliaFinance and Banking

Will a contractual deemed service of email provision ever provide a Respondent more than the statutory maximum 10 Business Days for service of a Payment Schedule? The Court of Appeal's short answer is 'no'.

Background

Under section 14(4) of the Security of Payment Act 1999 (NSW) (SoP Act), a respondent must provide to the claimant a payment schedule within the shorter of the time required by the relevant construction contract or 10 business days after the payment claim has been served. If the respondent misses that window, then it is liable to pay the claimed amount on the due date for the progress payment to which the payment claim relates, a liability that can be enforced by the claimant under s 15(2)(a)(i) debt recovery proceedings.