Quantum meruit to the rescue? Maybe, but don't count on it.

Quantum meruit is a last resort & is only available when no enforceable contract exists, or work is performed outside the contract's scope.

AustraliaCorporate/Commercial Law

In the building and construction industry, certainty in contracts is the foundation for successful projects. But what happens when work is done without a formal contract, or outside the agreed scope, and disagreement ensues?

In that case, quantum meruit may come into play. Quantum meruit, which in Latin means, "as much as is deserved";, is a principle that allows you or someone else to claim reasonable payment for services or work provided. This principle is particularly significant for government agencies due to several factors:

  • Budget constraints: Government projects often have fixed budgets, making it diff icult to accommodate unexpected quantum meruit claims and agencies cannot often pay beyond allocated funds

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from