Liquidated damages clauses and proof of a "penalty clause"

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

To avoid paying liquidated damages as a "penalty clause", a party must prove they are extravagant and unconscionable.

AustraliaCorporate/Commercial Law

The recent WA Court of Appeal decision of Active Tree Services Pty Ltd v Electrical Resource Providers Pty Ltd [2014] WASCA 6 reminds us that a party seeking to avoid paying liquidated damages on the basis that it is a "penalty clause" has the onus to prove that the liquidated damages are extravagant and unconscionable.

ATS had a contract with WA's Western Power to provide clearing and removal services for vegetation around power lines. ATS engaged ERP to assist it in providing the vegetation clearing services.

The work involved was specialised, difficult and dangerous. Because the specialist contractors were difficult to re-deploy to other similar jobs, the contract required ATS to give 2 months notice of termination and pay an "Early Termination Fee" equal to 2 months' revenue in the event that notice was not given. ATS failed to give proper notice and the trial judge in the WA District Court awarded damages to ERP equal to the 2 months revenue.