The Calcutta High Court, in Kolkata Metropolitan Development Authority v. South City Projects (Kolkata) [APO 205 of 2023], upheld an arbitral award in favour of the respondent consortium, dismissing the appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 ("A&C Act").

IndiaLitigation, Mediation & Arbitration

Introduction

The Calcutta High Court, in Haldibari Tea Manufacturers LLP v. Mahindra Tubes Ltd. [CO 204 of 2024] rejected a challenge under Order VII Rule 11 of the Code of Civil Procedure (CPC) read with Section 12A of the Commercial Courts Act, 2015, and upheld the maintainability of a commercial suit filed by Haldibari Tea Manufacturers LLP against, inter alia, Mahindra Tubes Limited.

The High Court ruled that since the suit contemplated urgent interim relief and an application under Order XXXIX Rule 1 and 2 of the CPC had been filed simultaneously, the mandatory requirement of pre-institution mediation under Section 12A was not violated. In this article, we examine the facts of the case and the findings rendered by the High Court.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from