Waiver Of Subrogation – "Work" Versus "Non-Work"

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

The Indiana Court of Appeals has been busy addressing the scope of subrogation waivers.

United StatesReal Estate and Construction

The Indiana Court of Appeals has been busy addressing the scope of subrogation waivers.  The latest decision is an argument over whether the waiver extends to property that is not part of the contractor's "Work" (as defined in the AIA contract form used by the parties).  The court1 decided to follow what has been referred to as the majority rule on this issue, and held that the waiver of subrogation bars subrogated claims concerning non-Work property.  I wrote about a similar case on a related issue just last month.

The project was to renovate the Jefferson County courthouse.  A devastating fire arose during construction, from soldering work on copper roofing materials, causing $6 million in damage.  Some of the damaged property was beyond the scope of the project, or the "Work" as defined in the AIA contract form. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from