Tennessee Supreme Court Clarifies When Liquidated Damages Are Enforceable

The Tennessee Supreme Court has issued a landmark ruling clarifying when liquidated damages clauses are enforceable, establishing a presumption of validity when contracts state that actual damages would be difficult to ascertain and the agreed amount is reasonable. The decision resolves long-standing conflicts in Tennessee case law by placing the burden of proof on parties challenging such provisions and confirms that incremental increases to earnest money, when supported by consideration, are not automatic

United StatesReal Estate and Construction

Key Takeaways

  • Liquidated damages clauses are presumed enforceable in Tennessee when the contract states that actual damages would be difficult or impossible to ascertain and that the agreed amount is a reasonable estimate of damages.
  • The burden of proof is on the party challenging the clause. That party must show, by a preponderance of the evidence, that the provision is an unenforceable penalty, and the parties do not need a metric or formula explaining how they arrived at the amount.
  • Incremental increases to earnest money, when supported by consideration, are not automatically penalties. Companies should review their real estate purchase agreements and amendment ratification language to make full use of the presumption.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from