Arbitrator Jurisdiction: Don’t Just Talk The Talk, But Walk The Walk

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

Can a party repeatedly object to the arbitrator’s jurisdiction, continue in the arbitration process, and then contest the arbitration award after the fact?

United StatesLitigation, Mediation & Arbitration

Can a party repeatedly object to the arbitrator's jurisdiction, continue in the arbitration process, and then contest the arbitration award after the fact? That issue was recently considered by a federal court in Michigan.1 The court held that a subcontractor who filed a counterclaim and participated in discovery and arbitration hearings, had waived its rights to contest the jurisdiction of the arbitrator, despite written objections periodically placed on the record. This is another warning to those who want or need to seriously challenge the jurisdiction of arbitrators: don't continue in the process if you're going to object to arbitrability!

Target, the subcontractor, marked up the original subcontract but did not modify the arbitration clause. Lakeshore, the general contractor, never agreed to the marked-up version. No subcontract was ever signed. Just the same, work went forward with numerous references to the subcontract, until Lakeshore terminated