Virginia Public Contractors Beware: Fourth Circuit Upholds Cap On Contractor Recovery For Changed Work

Recently, in Carnell Constr. Corp. v. Danville Redevelopment & Housing Auth., the federal appellate court covering West Virginia, Virginia and the Carolinas upheld a trial court’s determination.

United StatesGovernment, Public Sector

Recently, in Carnell Constr. Corp. v. Danville Redevelopment & Housing Auth., the federal appellate court covering West Virginia, Virginia and the Carolinas upheld a trial court's determination that a Virginia statute places a cap on the amount that a public works contractor can recover for any changed work, unless the state government previously approved, in writing, the changed work. Any contractors performing (or considering performing) on a Virginia public contract must beware of the Carnell case in this regard and the potentially inequitable results of this decision.

The dispute arose out of a construction contract between Carnell Construction Corporation ("Carnell") and the Danville, Virginia Redevelopment Housing Authority (the "Housing Authority"). Project delays occurred soon after the $793,541 contract was awarded, with each party attributing fault for the delays to the other. Eventually, the Housing Authority advised Carnell that it would not extend the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from