Government contractors will want to review their teaming
agreements following the recent decision in Cyberlock
Consulting, Inc. v. Info. Experts, Inc.. In
Cyberlock, the U.S. District Court for the Eastern
District of Virginia held that a teaming agreement expressing that
the parties would negotiate a subcontract in the future was just an
"agreement to agree" and thus unenforceable. As a
result, Cyberlock, the prospective subcontractor on a contract
award from the U.S. Office of Personnel Management
("OPM"), could not require Information Experts, its
teaming partner and the prime contractor under the contract, to
agree on a subcontract providing Cyberlock 49 percent of the work
from OPM. The Cyberlock decision confirms government
contractors cannot rely on generic teaming agreements to guarantee
the promise of work under a subcontract. Instead they need to
negotiate more definite subcontract terms and conditions that will
be effective upon a prime contract award, or