ARTICLE · 26 OCTOBER 2026

GAO Upholds Navy Sole-Source Award To Preserve Defense Industrial Base Capacity

The Government Accountability Office recently affirmed the Navy's authority to preserve critical manufacturing capacity through sole-source contracting, even when an incumbent contractor remains capable of meeting requirements. This decision addresses whether defense agencies must prove a manufacturer will exit the market without a contract, or whether a reasonable basis for industrial mobilization concerns suffices. The ruling has significant implications for contractors investing in specialized defense ma

United StatesGovernment, Public Sector

Key Takeaways

  • GAO affirmed the Navy’s authority to use sole-source contracting to preserve critical manufacturing capacity. GAO denied a protest challenging the Navy’s decision to award a contract to a second qualified manufacturer of submarine escape suits, finding that the award was reasonably justified by industrial mobilization needs.
  • Agencies need not prove that a manufacturer will exit the market without a contract. GAO concluded that the Navy was not required to conduct a financial analysis establishing that the manufacturer would cease production absent the award, provided the agency had a reasonable basis for its determination.
  • The decision highlights the importance of supply-chain resilience in defense procurement. Contractors should recognize that agencies may rely on industrial mobilization authority to maintain alternative sources of supply, even when an incumbent contractor is capable of meeting the government’s requirements.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from