The Situation
: The Government Accountability Office (GAO) recently held that
a bid need not contain all of the information listed in the Federal
Acquisition Regulation (FAR clause 52.225-9) to qualify for the
"unreasonable cost" exception to the Buy American Act
(BAA).
The Result: The decision requires agencies to
analyze the contents of a bid, rather than mechanically rejecting
it on a technicality.
Looking Ahead: A company can protest a rejected
bid so long as the missing information would not allow the bidder
to later alter its price or relative standing.
The GAO recently sustained a protest finding that it was
unreasonable for the Department of Energy (DOE) to reject a bid
simply because it failed to strictly comply with all of the
requirements for an exception to the BAA. In Addison Constr. Co., B-416525 (Sept. 4, 2018),
Addison Construction Company submitted a bid to construct a
capacitor bank for DOE in Arizona. Addison's bid informed