On Dec. 18, 2024, the Senate approved the Fiscal Year National
Defense Authorization Act (FY25 NDAA), and the President signed it
on Dec. 23, 2024.
Section 885, "Proposal for Payment of Costs for Certain
Government Accountability Office Bid Protests," is
particularly notable because it raises the task and delivery order
bid protest jurisdictional threshold under 10 U.S.C. §
3406(f)(1)(B) from $25 million to $35 million for DoD orders.
Section 885 also requires the General Accountability Office
(GAO) and the Department of Defense (DoD) to submit a pilot program
proposal to Congress within 180 days of FY25 NDAA's enactment,
but it is silent on whether the pilot program will apply to small
businesses. The GAO and DoD would be required to include and
establish an enhanced pleading standard in the pilot program
proposal that a protestor must meet before obtaining the
administrative record. While it's unclear how the enhanced
pleading standard will take shape, its goal