Earlier this week, the U.S. Court of Federal Claims ruled
against a bid protester seeking to stop performance on NASA's
$6.8 billion commercial space program. The court's ruling
upheld NASA's unusual decision to override the automatic stay
of contract performance during a GAO bid protest.
Sierra Nevada Corp. protested to the GAO its exclusion from
continuing NASA efforts to fund development of commercial
spacecraft. NASA awarded the continuing work to Boeing Co. and
Space Exploration Technologies.
Typically, disappointed offerors or bidders file bid protests
with the GAO because of the federal statute known as the
Competition in Contracting Act (CICA). Among other things, CICA
requires agencies to stop performance of contracts that are timely
protested — commonly known as the "CICA stay."
However, the statute also provides that agencies may override the
CICA stay upon a written finding that "performance of the
contract is in the best interests of the United