Chicago Mayor Signs City Executive Order Creating Enhanced Regulatory Review For Data Centers, Calls For Temporary Moratorium

Greenberg Traurig
Greenberg Traurig
Contributor
Greenberg Traurig

Greenberg Traurig

Greenberg Traurig, LLP has approximately 3,200 lawyers across 51 locations in the United States,...

View firm profile
Explore more from Greenberg Traurig

On Aug. 11, 2026, Chicago Mayor Brandon Johnson signed Executive Order No. 2026-5 (the order), directing city departments to take immediate steps to strengthen oversight of data center development and calling on the Chicago City Council to enact a temporary moratorium on new data centers and the material expansion of existing facilities.

United StatesGovernment, Public Sector
Go-To Guide:
  • The executive order took effect immediately upon publication and directs enhanced regulatory review of data center development in Chicago.
  • The city’s chief sustainability officer must promulgate both air pollution and noise rules within 90 days (unless the mayor grants an extension).
  • The city’s Department of Planning and Development (DPD) must conduct enhanced review of all planned developments that include data centers, with mandatory 60-day departmental consultation.
  • The Data Center Task Force must deliver recommendations and proposed regulatory language by March 15, 2027, subject to extension by the mayor.
  • The proposed moratorium and material expansion standard may create pipeline and construction schedule risk.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from