No question, the ongoing COVID-19 pandemic is giving rise to
multitudes of delay claims (along with claims of other varieties)
by contractors against the federal government. Since the effects of
the COVID virus did not begin to be felt until March of this year,
even the earliest of these virus-related claims have yet to work
their way through the dispute resolution process. Consequently, our
ability to project how the courts and boards will approach these
claims is limited. Recently, however, the Civilian Board of
Contract Appeals offered a bit of a preview of how pandemic delay
claims may be addressed in Pernix Serka Joint Venture v. Department
of State, 20-1 BCA ¶ 37589, CBCA No. 5683 (April 22, 2020).
This case concerning delay caused by the 2014 outbreak of the Ebola
virus in Africa, is instructive for contractors seeking
compensation for COVID delays.