ARTICLE · 22 MAY 2025

Bid Protest Minute – Protest Underscores Importance Of Prejudice, Past Performance Requirements, And Protest Timing

On May 7, the Government Accountability Office (GAO) dismissed a protest challenging the terms of a solicitation for being unduly restrictive.

United StatesGovernment, Public Sector

On May 7, the Government Accountability Office (GAO) dismissed a protest challenging the terms of a solicitation for being unduly restrictive. The protest highlights three important considerations that contractors should understand when deciding to file a protest:

  1. Competitive prejudice is a required element of any viable protest.
  2. Under the Federal Acquisition Regulation (FAR), an agency cannot fault a bidder for lacking relevant past performance.
  3. Pre-award protests are available to potential protesters who wish to challenge the ground rules of a procurement, but they must be submitted prior to the closing date for quotations.

Below, we discuss the solicitation requirements, the merits of GAO's decision to dismiss the protest, and expand on the considerations contractors should weigh when determining whether to initiate a protest.