On December 21, the Government Accountability Office (GAO) dismissed a protest by ELS, an unsuccessful bidder on a Department of Defense (DOD)...

United StatesGovernment, Public Sector

On December 21, the Government Accountability Office (GAO) dismissed a protest by ELS, an unsuccessful bidder on a Department of Defense (DOD) task order opportunity, concluding that it did not have jurisdiction to consider it.

GAO reasoned that because "the value of the task order [was] below $25,000,000 . . . it does not have jurisdiction to consider the protest." One would think the $25 million threshold applicable to protests of DOD task orders (the threshold is $10 million for civilian agency task orders) would be easily understood and simple to apply. However the ELS decision shows it may not always be as straightforward as it sounds.

The Procurement at Issue

The Navy's Naval Sea Systems Command (NAVSEA) issued a Request for Task Order Proposals (RTOP) to holders of the SeaPort Next Generation indefinite-delivery, indefinite-quantity (IDIQ) contract seeking to procure administrative and engineering support services. The RTOP sought to award one