Share on LinkedInShare on LinkedIn

ARTICLE · 21 OCTOBER 2019

Allowability Of Bid Protest-Related Costs Subject To Mitigation

Arnold & Porter
Arnold & Porter
Contributor
Arnold & Porter

Arnold & Porter

With over 1,000 lawyers across 16 offices worldwide, Arnold & Porter is renowned for its...

View firm profile
Explore more from Arnold & Porter

What happens when the existence of a bid protest impacts contract administration? The Armed Services Board of Contract Appeals (ASBCA or the Board) recently addressed such a scenario in Advanced...

United StatesGovernment, Public Sector

What happens when the existence of a bid protest impacts contract administration? The Armed Services Board of Contract Appeals (ASBCA or the Board) recently addressed such a scenario in Advanced Global Resources, LLC, ASBCA No. 62070,1 holding that a contractor cannot recoup the costs of idle labor during the period of a bid protest.

Background

Advanced Global Resources, LLC (AGR) received a contract for information technology support services on December 14, 2017, and Task Order 1 under that contract on December 19, 2017. The day after contract award, AGR entered into an employment contract with Mr. Michael McKissick. By December 22, 2017 the disappointed incumbent protested the award, and the contracting officer notified AGR to stop work. At the time of receipt of the stop work order, AGR had performed only unbillable transition work.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from