What happens when the existence of a bid protest impacts
contract administration? The Armed Services Board of Contract
Appeals (ASBCA or the Board) recently addressed such a scenario in
Advanced Global Resources, LLC, ASBCA No. 62070,1
holding that a contractor cannot recoup the costs of idle labor
during the period of a bid protest.
Background
Advanced Global Resources, LLC (AGR) received a contract for
information technology support services on December 14, 2017, and
Task Order 1 under that contract on December 19, 2017. The day
after contract award, AGR entered into an employment contract with
Mr. Michael McKissick. By December 22, 2017 the disappointed
incumbent protested the award, and the contracting officer notified
AGR to stop work. At the time of receipt of the stop work order,
AGR had performed only unbillable transition work.