ARTICLE · 23 OCTOBER 2017

Court Declines To Vacate Environmental Assessment Of Dakota Access Pipeline, Permitting Oil To Flow During Remand

Hogan Lovells Cadwalader
Hogan Lovells Cadwalader
Contributor
Hogan Lovells Cadwalader

Hogan Lovells Cadwalader

Hogan Lovells Cadwalader is a global law firm trusted by clients to deliver on complex, high-stakes...

View firm profile
Explore more from Hogan Lovells Cadwalader

The court's decision—which permits the EA and a related easement granted by the Corps to remain in effect—will allow the pipeline to continue operating during the remand period.

United StatesEnvironment

On October 11, 2017, the United States District Court for the District of Columbia declined to vacate the U.S. Army Corps of Engineers' ("Corps") Environmental Assessment ("EA") of the Dakota Access Pipeline while the agency addresses, on remand, certain deficiencies in the EA identified in a prior ruling.1  The court's decision—which permits the EA and a related easement granted by the Corps to remain in effect—will allow the pipeline to continue operating during the remand period.

The court stated that although vacatur is the "presumptive remedy" when an agency action violates the National Environmental Policy Act ("NEPA"), a two-prong test must be applied to determine whether vacatur during remand would be appropriate in this case.  The court considered: (1) the seriousness of the EA's deficiencies, and the likelihood that the Corps would be able to substantiate its prior conclusions on remand; and (2) the disruptive consequences of vacatur.  The court concluded