It has been 10 month waiting after Decision 11/QDD-TTg expired,
now the Prime Minister has issued Decision 13/2020 on the incentive
mechanism for solar power development. We would like to update the
very new key issues as follows:
1. FIT scheme
Following notification No. 402/TB-VPCP of Prime Minister Nguyen
Xuan Phuc, now FIT scheme is confirmed that it only applies for the
following projects:
– For grid-connected projects: the projects that: (i) has
in-principle investment decision before 23/11/2019, and (ii) COD of
the whole or part(s) of project from 01/7/2019 to 31/12/2020.
– For grid-connected projects in Ninh Thuan: (i) the projects
that were included into power development plans, (ii) COD before
01/01/2021, and (iii) the accumulated capacity not exceeding 2,000
MW.