On August 3, 2026, Texas Governor Greg Abbott directed the Public Utility Commission of Texas ("PUCT") and the Electric Reliability Council of Texas ("ERCOT") to pause approvals of any pending data centers while the PUCT and ERCOT conduct an audit of every data center advancing through ERCOT's interconnection process.
Overview of the Directive
The directive, issued by letter to the PUCT chairman and ERCOT president, requires PUCT and ERCOT to undertake a comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process "before any additional data centers are approved to move forward." The directive, which cites the significant volume of data center connection requests pending before ERCOT, states that any data center project that does not comply with PUCT and ERCOT requirements must be denied connection to Texas's electric grid.