Neither PURPA nor FERC's regulations explicitly mention energy storage as an energy resource type that can make a facility eligible for QF status.

United StatesEnergy and Natural Resources

On August 31, 2018, NorthWestern Corporation (NorthWestern) petitioned the Federal Energy Regulatory Commission (FERC or Commission) to revoke the qualifying small power production facility (QF) status of four wind projects planning to integrate batteries at their respective sites, raising new questions for the treatment of energy storage under the Public Utility Regulatory Policies Act of 1978 (PURPA). At issue is whether wind or solar generation facilities and co-located storage should be treated as a single QF—and if so, how to calculate the facility's aggregate "power production capacity"—or whether co-located storage facilities should be treated as separate QFs.

Given the Commission's ongoing review of its PURPA regulations, the instant case provides FERC with an opportunity to clarify its limited precedent on PURPA's treatment of energy storage. FERC's ruling could thus have immediate impacts for project developers seeking to obtain QF status for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from