It is also not entirely clear how this proposal would work in practice.

United StatesEnergy and Natural Resources

On August 18, 2016, PJM Interconnection, L.L.C. ("PJM") presented a proposal to its stakeholders outlining a possible mechanism for mitigating the potential impact on capacity prices in the PJM market of generation units receiving revenues from state-regulated programs.1  The proposal, in the form of a short white paper, was presented as part of a symposium on market efficiency and public policy.2  The potential impact of state-supported generation on Regional Transmission Organization/Independent System Operator ("RTO/ISO") capacity markets has become increasingly relevant as state regulators and lawmakers consider adopting programs to provide revenues outside of the RTO/ISO capacity markets to support the construction of new generation and, more recently, the retention of existing generation. States are considering providing such out-of-market revenues to promote a variety of public policy objectives, including price stability and environmental and clean energy

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from