Share on LinkedInShare on LinkedIn

ARTICLE · 20 SEPTEMBER 2017

Lack Of Quorum Costs East Kentucky Power Cooperative In PURPA Dispute

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

On November 4, 2016, EKPC submitted its initial application seeking to terminate the purchase requirement in its service territory for QFs of more than 20 MW.

United StatesEnergy and Natural Resources

The Federal Energy Regulatory Commission (FERC or the "Commission") recently restored its quorum with the swearing in of Commissioners Neil Chatterjee and Robert Powelson, but the casualties from the six-month, quorumless period continue to pile up. East Kentucky Power Cooperative (EKPC), a generation and transmission cooperative in PJM Interconnection, L.L.C., is the latest victim. On September 7, 2017, FERC granted EKPC's application seeking to terminate its obligation to purchase electric energy and capacity from qualifying small power production facilities (QFs) with a net capacity in excess of 20 MW (the "September 2017 Order"). The September 2017 Order represents a pyrrhic victory of sorts for EKPC, though, because FERC ruled that the termination does not apply to two Kentucky QFs that protested the application — a result that would not have occurred if FERC had a working quorum earlier in the year.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from