FERC Staff Questions Wind Farms On Calculation Of PURPA's One-Mile Rule

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

On June 9, 2017, Beaver Creek Wind II, LLC and Beaver Creek Wind III, LLC responded to a deficiency letter from FERC staff seeking further information on Beaver Creek's calculation...

United StatesEnergy and Natural Resources

On June 9, 2017, Beaver Creek Wind II, LLC and Beaver Creek Wind III, LLC (together, "Beaver Creek") responded to a deficiency letter from the Federal Energy Regulatory Commission (FERC or the "Commission") staff seeking further information on Beaver Creek's calculation of the "one-mile" rule in its applications for certification as qualifying small power production facilities (QFs). At issue is Beaver Creek's proposed "weighted geographic center" methodology used to calculate the distance between wind projects consisting of multiple pieces of geographically dispersed electric generating equipment (i.e., wind turbines) for the purposes of applying the one-mile rule under the Public Utility Regulatory Policies Act of 1978 (PURPA). With a potential FERC quorum on the horizon, the instant case provides the new FERC commissioners with an opportunity to establish a preferred methodology, if any, for measuring one mile for purposes of PURPA. As such, the outcome could have

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from