ARTICLE · 29 MARCH 2021

FERC Reverts To Its Traditional "Send Out" Analysis For Determining "Power Production Capacity" Of Small Power Production QFs

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

On March 19, 2021, a divided Federal Energy Regulatory Commission (FERC or the "Commission") reverted to its long-standing "send out" analysis for determining the "power production capacity"...

United StatesEnergy and Natural Resources

On March 19, 2021, a divided Federal Energy Regulatory Commission (FERC or the "Commission") reverted to its long-standing "send out" analysis for determining the "power production capacity" of a small power production qualifying facility (QF) under the Public Utility Regulatory Policies Act of 1978 (PURPA) and FERC's implementing regulations.1 Commissioners James Danly and Mark Christie voted against the result, with Commissioner Danly writing separately in dissent.

In September 2020, FERC had abruptly changed course from evaluating the size of a small power production facility based on the maximum energy output that the facility could inject through its interconnection point, holding that the "power production capacity" of a facility was its "maximum net power production capacity" as calculated in Section 7 of FERC's Form No. 556 (Certification of Qualifying Facility (QF) Status for a Small Power Production or Cogeneration Facility), adjusted "only

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.