On May 17, 2012, the Federal Energy Regulatory Commission ("FERC" or "Commission") issued an "Order on Rehearing and Clarification" reaffirming its Order No. 1000.

United StatesEnergy and Natural Resources

On May 17, 2012, the Federal Energy Regulatory Commission ("FERC" or "Commission") issued an "Order on Rehearing and Clarification" reaffirming its Order No. 1000,1 which the Commission issued in August 2011 as a major reform of FERC policies governing the planning for, and cost treatment of, new electric transmission projects. The May 17 Order, Order No. 1000-A,2 denied requests for rehearing that had challenged Order No. 1000's central directives. FERC also clarified certain elements of Order No. 1000's requirements.

Overview of FERC Order No. 1000

Order No. 1000 requires each Public Utility Transmission Provider ("Transmission Provider")

  1. To participate in a regional planning process that evaluates transmission alternatives based on the principles of FERC's Order No. 8903 and to produce a regional transmission plan that evaluates, inter alia, transmission needs driven by public policy requirements that are established by state or federal laws or regulations