Share on LinkedInShare on LinkedIn

ARTICLE · 29 JUNE 2026

FERC Directs Southwest Power Pool To Revise Tariff To Expedite Data Center Development

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Southwest Power Pool, Inc. (SPP) directing SPP and SPP transmission owners to show cause as to why SPP’s tariff should not be unjust...

United StatesEnergy and Natural Resources

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Southwest Power Pool, Inc. (SPP) directing SPP and SPP transmission owners to show cause as to why SPP’s tariff should not be unjust and unreasonable (Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (Order)) because it fails to sufficiently:

  • address the evaluation of alternative transmission technologies in the large load transmission study process;
  • mitigate the risk of cost shifting among transmission customers due to large load, including providing transparency regarding the assignment of network upgrades and requiring a pro forma cost recovery agreement that would ensure that large load customers bear the risks and costs of network upgrades needed to provide them with transmission service;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from