ARTICLE · 05 NOVEMBER 2019

Continued Uncertainty For Domestic, Commercial-Scale Offshore Wind

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

Recent demands by the U.S. Department of the Interior are delaying agency approval of the first commercial-scale offshore wind farm in the United States.

United StatesEnergy and Natural Resources

Recent demands by the U.S. Department of the Interior are delaying agency approval of the first commercial-scale offshore wind farm in the United States. The project under review is the Vineyard Wind project, an 800-megawatt wind farm off the shore of Massachusetts ("Vineyard Project"). While Europe has been leading the offshore wind charge with more than 105 wind farms (with capacity sizes ranging up to 650 megawatts) and a total of about 18,500 megawatts online, the offshore wind industry in the United States is a nascent industry, with only one 30-megawatt operational offshore wind farm, the Block Island Wind Farm. The sheer magnitude of the Vineyard Project, which is more than 26 times the capacity of the Block Island Wind Farm, makes it a monumental and groundbreaking project in the United States.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from