In Bauwnes v. Revcon Technology Group, Inc., the U.S.
Court of Appeals for the Seventh Circuit held that the trustees of
a multiemployer pension plan could not agree to an employer's
installment payment plan of its withdrawal liability after the
trustees had demanded full payment following the employer's
default. This "no good deed goes unpunished"
decision will likely make trustees much less likely to agree to
subsequent payment plans after finding an employer in default.
Background
Under the Employee Retirement Income Security Act, once a
multiemployer plan determines that an employer has withdrawn from
the plan, the plan sponsor must "as soon as practicable"
provide the withdrawing employer with the total amount of the
withdrawal liability and a schedule of payments.1
If an employer fails to cure the non-payment of withdrawal
liability within 60 days of receiving notice from the plan sponsor
of the failure to make payment, the plan sponsor may deem