A question often asked by shipowners is to what extent they can legitimately walk away from orders of newbuildings or, as an alternative course of action, can they delay the construction of the vessel?

United KingdomTransport

Originally published in Lloyd's List, 2 September 2009.

A question often asked by shipowners is to what extent they can legitimately walk away from orders of newbuildings or, as an alternative course of action, can they delay the construction of the vessel?

Shipowners are often raise these legal inquiries prompted by the hope that the market will pick up in the future and for buyers who have been unable to organise financing due to the decline in ship values.

Answers will depend on the terms of each contract. However, if the buyer is locked into a contract price, he will almost certainly be unable to terminate, even if he decides to abandon the pre-delivery instalments already paid and just walk away. The shipbuilder in such cases may be entitled to reject the buyer's breach and keep building the ship, invoicing the buyer for the stage payments and the delivery instalment, as each falls due.