The Supreme Court in RTI Ltd v MUR Shipping BV [2024] UKSC 18 ruled that MUR was justified in rejecting RTI's non-contractual offer under a force majeure clause, emphasizing contractual certainty and limits to reasonable endeavours.

United KingdomTransport

This week, the Supreme Court issued its decision in the highly anticipated RTI Ltd (Respondent) v MUR Shipping BV (Appellant)[2024] UKSC 18 proceedings.

The Supreme Court unanimously allowed the appealand held that MUR was allowed to reject RTI's offer of non-contractual performance under a force majeure clause (namely to make payments in an alternative currency and compensate MUR for any additional costs) and such an offer could not amount to reasonable endeavours to cure a force majeure event.

Background

The background the matter is well known and has already been well summarised in our previous commentary of the Court of Appeal's decision in 2022 as well as the Supreme Court press release dated 15 May 2024. In short and with thanks to these two documents: