ARTICLE · 13 MAY 2026

When The Regulator Says No: The Impact Of Building Safety Regulator Rejections On Construction Litigation

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

A recent decision of the Technology and Construction Court (TCC) provides important guidance on the intersection of the new building safety regulatory regime and the Court's case management powers in high-value...

United KingdomReal Estate and Construction

A recent decision of the Technology and Construction Court (TCC) provides important guidance on the intersection of the new building safety regulatory regime and the Court's case management powers in high-value construction disputes.

In GS Woodland Court GP 1 Ltd & Anor v RGCM Ltd & Ors [2026], the TCC considered the case management consequences of the Building Safety Regulator (BSR) rejecting a claimant's proposed remedial scheme for a Higher Risk Building (HRB).

This case is significant: it is one of the first TCC judgments to grapple directly with the case management implications of BSR delays. It makes clear that the BSR's decision on a remedial scheme is a factual matter that may materially influence how a court manages proceedings, particularly in relation to quantum. For parties procuring remedial works to HRBs, this illustrates the risk that BSR delays or adverse decisions can derail even well-advanced litigation timetables.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from