In this edition of Building Safety Act 2022 (BSA) briefings we consider the Upper Tribunal decision in Unsdorfer v Octagon[JC1] . Whilst the decision dates back to 2024 it is useful in providing some clarity on the roles and responsibilities of “managers”, “special measures managers” and “accountable persons” appointed in relation to higher-risk buildings (HRBs).

United KingdomReal Estate and Construction

In this edition of Building Safety Act 2022 (BSA) briefings we consider the Upper Tribunal decision in Unsdorfer v Octagon[JC1] .

Whilst the decision dates back to 2024 it is useful in providing some clarity on the roles and responsibilities of “managers”, “special measures managers” and “accountable persons” appointed in relation to higher-risk buildings (HRBs).

The question considered by the Upper Tribunal was whether a manager appointed under s.24 of the Landlord and Tenant Act 1987 (LTA 1987) could be an “accountable person” within the meaning of s72 of the BSA.

In summary, even where day-to-day control of an HRB has been handed to a manager, the BSA’s obligations of the accountable person can remain with the freeholder.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from