ARTICLE · 07 OCTOBER 2021

What's The Deadline For Challenging The Final Statement Under JCT Contracts? (...And How To Ensure Your Challenge Is Effective)

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In the recent decision of CC Construction Ltd v Mincione [2021], the Technology and Construction Court (the TCC) considered various issues relating to the interpretation of standard Joint Contract Tribunal (JCT) wording.

United KingdomReal Estate and Construction

In the recent decision of CC Construction Ltd v Mincione [2021], the Technology and Construction Court (the TCC) considered various issues relating to the interpretation of standard Joint Contract Tribunal (JCT) wording. Of particular interest are those parts of the judgment relating to the due date for final payment, which determines the deadline for challenging the Final Statement, and the need for the written challenge to be clear and unambiguous to ensure it constitutes an effective challenge.

Read our analysis below.

Summary

Points to watch out for under JCT standard wording:

  • Don't miss the deadline for challenging the Final Statement in order to prevent it becoming conclusive - assume you have to work to the earliest possible due date for final payment (under e.g. clause 4.24.5 of JCT DB 2016).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.