Weston Homes Plc v Henley Developments 211 Limited, Henley Property Investments (UK) LLP

Gatehouse Chambers
Gatehouse Chambers
Contributor
Gatehouse Chambers

Gatehouse Chambers

Gatehouse Chambers is a leading commercial set with expertise spanning commercial dispute...

View firm profile
Explore more from Gatehouse Chambers

In Weston Homes Plc v Henley Developments, the court ruled that the Buyer could terminate the contract and reclaim the deposit, even if the termination resulted from their own breach. The decision emphasized that the contract's clear terms prevailed over general contract construction principles, confirming that the right to terminate was not limited by prior breaches. This highlights the importance of understanding the precise language of contract terms when determining rights and obligations.

United KingdomReal Estate and Construction

Weston Homes Plc v Henley Developments 211 Limited, Henley Property Investments (UK) LLP

Background

The claimant ('the Buyer') agreed to buy freehold property in Ebbsfleet, Kent ('the Property') from the first defendant ('the Seller') under a conditional contract of sale dated 21 June 2022 ('the Contract'), and paid a deposit of £870,000 ('the Deposit').

Clause 23.2 of the Contract entitled either party to serve written notice terminating the contract "if the Compliance Date had not occurred by the expiry of the Relevant Period". In the event such a notice was served, the Seller was to repay the Deposit to the Buyer within 10 business days.

Clause 1.1 defined the Compliance Date and Relevant Period as follows:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from