ARTICLE · 09 OCTOBER 2008

Wembley: "Entire Contracts" And The Right To Be Paid

The main judgment was given last Monday in the Wembley case.

United KingdomReal Estate and Construction
Julian Bailey
Julian Bailey

The main judgment was given last Monday in the Wembley case. The dispute between Multiplex and Cleveland Bridge raised a number of important legal issues. One was whether Cleveland Bridge, who walked off the project, were entitled to be paid for work they performed prior to abandoning it.

  • Under the contractual arrangements, Cleveland Bridge was entitled to be paid £12m for performing certain "lump sum" work.
  • Part-payment of the £12m was to be made monthly, as the work was performed. The amount due was that which was certified for the particular month.
  • Cleveland Bridge walked off the job in early August 2004. But just before doing so they submitted a claim for payment for the work performed up to 27 July 2004.