Waiver of Time Bar Clause Upheld: City Inn Revisited (Again) (Part 2 of 2)

The decision of the Inner House in City Inn v Shepherd Construction delivered on 22 July is important for its treatment not only of the extension of time clause in JCT style contracts but also of a time bar clause.

United KingdomReal Estate and Construction
Caroline Cummins
Caroline Cummins

The decision of the Inner House in City Inn v Shepherd Construction delivered on 22 July is important for its treatment not only of the extension of time clause in JCT style contracts but also of a time bar clause (for our Law-Now on the former: click here.  For our Law-Now on the decision of the Outer House delivered in 2007 in relation to the time bar clause, click here.

The decision in the Outer House concerning the time bar clause may be summarised thus. Clause 13 in the contract between the parties required Shepherd as contractor within ten days of receiving an instruction to give the Architect details of its estimated effect, failing which Shepherd would lose any entitlement to extend the completion date for the works.  If Shepherd's entitlements arising from the instruction were not agreed within five days the Architect might withdraw the instruction or require Shepherd to proceed anyway.  Shepherd gave a timely but non-compliant notice. The judge decided

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from