Use Of Time Bar - In Other Words "giving Notices On Time" Under Construction Contracts

Both NEC and FIDIC contracts expressly state that notice of a claim is a "condition precedent".

United KingdomReal Estate and Construction

Both NEC and FIDIC contracts expressly state that notice of a claim is a "condition precedent".

The 2017 suite is very prescriptive and now contains a number of other detailed processes and procedures that set out exactly what is expected of each of the parties and the consequences if they fail to comply. In some cases, non-compliance triggers a time bar.

FIDIC 2nd edition 2017 contains 5 time bar clauses in relation to Claims and dispute resolution process and 1 time bar in relation to amounts due in the Final Payment Certificate.

Key changes in FIDIC 2nd Edition 2017 are;

  • time bars apply to both Parties, and
  • circumstances that the claiming Party can challenge in justifying late submission of a Notice of Claim (Sub-clause 20.2.5) – prejudiced, prior knowledge of the event (or circumstance) or the contractual (or other legal basis) of the Claim,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from